Extension post # 10 – finito!

Four and a half months later and we’re pretty much there. It feels sooooo good. We’ve still got a few things to buy/do before it’s 100% finished but, for now, we’re just enjoying it!


Pre-extension, the kitchen was our least favourite room in the house, by far. It was tiny, the units were falling apart, and only 1 of the gas hobs worked. We now have the kitchen of our dreams and feel incredibly lucky!

Being the intensely sad people that we are, we’ve been speaking about having a range cooker and kitchen island for a few years. Cooking is now a joyful experience and so we fight over who gets to be chef. We eat sat at the island most nights which is so, so much nicer than being slumped on the living room sofa like we used to be.

One of the jobs still do to is tiling the kitchen wall. We’re going to use these tiles in a herringbone pattern – wish me luck, I’ll need it.

We went for Karndean LVT flooring which was pricey but looks great and is easy to clean. Apparently it lasts forever but this furry fella may have other ideas.

Opposite the kitchen we’ve got a wee seating area. One day I’ll make a coffee table to go here but for now it works well just as a place to flop. Basil loves to chill here whilst barking at cats in the garden and watching his mother cook.

The door at the back of the kitchen leads to a small utility room.

Initially, I wasn’t fussed about having a utility, but I’m glad that Haz pushed for it because it’s so handy to have this space separate from the kitchen. Plus, it’s a great place to leave a muddy dog to dry off.

As part of the work, a loo was sneaked in under the stairs. Whilst cat swinging isn’t an option in here, not having to go upstairs for a wazz is a well nice.

From outside, the extension looks really cosy. I’ll finish the patio in spring once the earth sat in the pond that used to be on the left hand side has had chance to settle over winter. I should probably give the patio a good clean…


We’re so chuffed with how the extension has transformed our home. Although, having said that, I’m hoping that it’ll be many years until we have any more building work done 🙂

Once we’ve finished everything, I’ll do a post on where we got stuff from. I may also do a post about how much everything cost as I’m sure that’ll be helpful for people planning on having similar work done.

Categories
Uncategorized

Extension post #7 – weeks 6 & 7

Not entirely sure where to start on this one as about 6,911 things have happened since my last post. There are only a couple more weeks of the builder/electrician/plumber being around so the focus is now moving to us for stuff like fitting the kitchen, decorating, getting the flooring laid etc. so it’s time to roll our sleeves up.


Crack, crack, crack city

Week 6 started with a worrying discovery. After living away from home for a few days whilst the back wall was knocked through and steels were added, we found that some pretty confident looking cracks had appeared in the two upstairs walls that sat on the 2 walls that had been knocked through.

We’d read about it being common for small cracks to appear as the walls settle between being supported by acrows and sitting on the steel joists. But our cracks aren’t exactly hairline and at their worst are 3mm wide. Needless to say, we were pretty worried about this so had a natter with the builder. He seemed very casual about them and said that they’d just need to be skimmed over.

We were still worried so I shared images of the cracks on a forum to get a second opinion and the consensus was that the cracks are larger than should be expected and that they’d need to be properly assessed. This could have brought the build to a standstill and ended up costing a lot of money. However, fortunately, Jim from building control came round early this week and after having a look said that it’s not a major concern, phew. For a belt and braces approach, he’s recommended that metals straps are inserted into the cracks and fixed in place with resin before being plastered over. It was such a relief to hear this!

Progress

With crack-gate out of the way, I can focus on all the awesome things that have happened in the last 2 weeks. First up, the floor of the extension has now been built up to the level of the existing floor so there’s no longer a massive drop when we walk into the extension.

First fix plumbing and electrics are sorted ahead of plastering. We spent a good half hour with the electrician, working out where to put spot lights, sockets and the kitchen pendants. We may have gone a bit overboard with sockets but it’s far better to have too many than too few, as we found when we moved into this place which only had one double socket per room.

The most exciting day was probably bi-fold day. Being the old man that I am, I’ve wanted to live somewhere with bi-fold doors out into the garden for quite a while so it was pretty great when they went in.

On the side of the house, the old back door has been blocked up and a new door fitted to the right of it, where the kitchen window was, which will lead into out mini utility.

To fill in the door left by taking the back door out, the builders used bricks they saved from knocking out the back wall. The blocked in door blends in really well so we’re chuffed with the job they’ve done on that. It’s a shame to lose the wee arched porch but to get a decent sized kitchen in it’s something we had to do.

ALSO, the stud wall that separates the utility from the kitchen has been put up, and the door opening has been prepared for a door that we picked up on FB marketplace for £20 which ties in perfectly with our other interior doors.

Soon after the guys had started in the stud wall, I took them a brew and it’s a good job I did. I suggested that we check the positioning of it and after measuring the space, there was too little space left for the kitchen units so they had to start again. Far better that way than having to rip it out once it was plastered or having to lose a kitchen unit!

The last couple of days of this week have totally transformed the space. On Thursday, all the plasterboard went up and on Friday, the walls were plastered. Quite an impressive operation with 5 blokes here on both days just cracking on with it.

If ever there was a time for an image slider, it’s now. The before photo was taken on Wednesday and the after on Friday! Mental.

Extension life

It seems only right to mention the joys of life with only one downstairs room in action. Food-wise, we’ve been making the most of the slow cooker and microwave which has required some innovative thinking. We’ve been using paper plates wherever possible, but inevitably there’s still a fair amount of stuff to wash up so our bathroom is now washing up HQ.

On top of the house being a mess, despite Haz’ best efforts to put dust sheets up theres still brick dust and general dirt covering every surface. Outside, our front garden is an absolute state and the back garden is worse. Stopping Basil from trapsing dirt throughout the house and picking up things in his mouth that he shouldn’t is currently our main past time activity.

Some good, however, has come from all of this. Our downstairs doors haven’t closed properly since we moved in so to help prevent Basil running wild I planed the doors last weekend so they’d close properly. The hallway to dining room door also needed a new door knob so I made what I think is quite a fetching industrial-chic door knob out of wood but Haz isn’t a fan. We’ll see who gets the last word.


So all-in-all, a bloody decent couple of weeks. The extension is unrecognisable vs just a few days together end the end is in sight. Next week, our kitchen is due to arrive so I’ve got some time off work to get it fitted which I’m really looking forward to. Once the plaster is dry we can also start painting so we really are moving towards having an actual functioning space – this is how excited we are.

Maybe a bit more deranged-looking than excited, but you get the idea.