Extension post #7 – weeks 6 & 7

Not entirely sure where to start on this one as about 6,911 things have happened since my last post. There are only a couple more weeks of the builder/electrician/plumber being around so the focus is now moving to us for stuff like fitting the kitchen, decorating, getting the flooring laid etc. so it’s time to roll our sleeves up.


Crack, crack, crack city

Week 6 started with a worrying discovery. After living away from home for a few days whilst the back wall was knocked through and steels were added, we found that some pretty confident looking cracks had appeared in the two upstairs walls that sat on the 2 walls that had been knocked through.

We’d read about it being common for small cracks to appear as the walls settle between being supported by acrows and sitting on the steel joists. But our cracks aren’t exactly hairline and at their worst are 3mm wide. Needless to say, we were pretty worried about this so had a natter with the builder. He seemed very casual about them and said that they’d just need to be skimmed over.

We were still worried so I shared images of the cracks on a forum to get a second opinion and the consensus was that the cracks are larger than should be expected and that they’d need to be properly assessed. This could have brought the build to a standstill and ended up costing a lot of money. However, fortunately, Jim from building control came round early this week and after having a look said that it’s not a major concern, phew. For a belt and braces approach, he’s recommended that metals straps are inserted into the cracks and fixed in place with resin before being plastered over. It was such a relief to hear this!

Progress

With crack-gate out of the way, I can focus on all the awesome things that have happened in the last 2 weeks. First up, the floor of the extension has now been built up to the level of the existing floor so there’s no longer a massive drop when we walk into the extension.

First fix plumbing and electrics are sorted ahead of plastering. We spent a good half hour with the electrician, working out where to put spot lights, sockets and the kitchen pendants. We may have gone a bit overboard with sockets but it’s far better to have too many than too few, as we found when we moved into this place which only had one double socket per room.

The most exciting day was probably bi-fold day. Being the old man that I am, I’ve wanted to live somewhere with bi-fold doors out into the garden for quite a while so it was pretty great when they went in.

On the side of the house, the old back door has been blocked up and a new door fitted to the right of it, where the kitchen window was, which will lead into out mini utility.

To fill in the door left by taking the back door out, the builders used bricks they saved from knocking out the back wall. The blocked in door blends in really well so we’re chuffed with the job they’ve done on that. It’s a shame to lose the wee arched porch but to get a decent sized kitchen in it’s something we had to do.

ALSO, the stud wall that separates the utility from the kitchen has been put up, and the door opening has been prepared for a door that we picked up on FB marketplace for £20 which ties in perfectly with our other interior doors.

Soon after the guys had started in the stud wall, I took them a brew and it’s a good job I did. I suggested that we check the positioning of it and after measuring the space, there was too little space left for the kitchen units so they had to start again. Far better that way than having to rip it out once it was plastered or having to lose a kitchen unit!

The last couple of days of this week have totally transformed the space. On Thursday, all the plasterboard went up and on Friday, the walls were plastered. Quite an impressive operation with 5 blokes here on both days just cracking on with it.

If ever there was a time for an image slider, it’s now. The before photo was taken on Wednesday and the after on Friday! Mental.

Extension life

It seems only right to mention the joys of life with only one downstairs room in action. Food-wise, we’ve been making the most of the slow cooker and microwave which has required some innovative thinking. We’ve been using paper plates wherever possible, but inevitably there’s still a fair amount of stuff to wash up so our bathroom is now washing up HQ.

On top of the house being a mess, despite Haz’ best efforts to put dust sheets up theres still brick dust and general dirt covering every surface. Outside, our front garden is an absolute state and the back garden is worse. Stopping Basil from trapsing dirt throughout the house and picking up things in his mouth that he shouldn’t is currently our main past time activity.

Some good, however, has come from all of this. Our downstairs doors haven’t closed properly since we moved in so to help prevent Basil running wild I planed the doors last weekend so they’d close properly. The hallway to dining room door also needed a new door knob so I made what I think is quite a fetching industrial-chic door knob out of wood but Haz isn’t a fan. We’ll see who gets the last word.


So all-in-all, a bloody decent couple of weeks. The extension is unrecognisable vs just a few days together end the end is in sight. Next week, our kitchen is due to arrive so I’ve got some time off work to get it fitted which I’m really looking forward to. Once the plaster is dry we can also start painting so we really are moving towards having an actual functioning space – this is how excited we are.

Maybe a bit more deranged-looking than excited, but you get the idea.

Categories
Doing it up

Before & after | Bedroom #1

The work on our bedroom started on move in day. After carrying Haz over the threshold, I legged it upstairs to rip up the carpet and begun prodding around. From a distance it looked in decent condition, but close-up it was really tired and unloved. Pretty much everything needed stripping bare before we could make it our own.

Anyway, you’re probably not here for all these words so without further ado, here’s what we did with it.

Before

After


The middle bit

We’re bloody well-chuffed with how it turned out after what felt like a bit of a slog. We spent all free evenings and weekends on it for 4 months which I guess isn’t that bad but the first 3 months were the shitty prep jobs – the last month was great! Here’s the main bits of work that we did.

Stripping, sanding, stripping, sanding, sanding, stripping… And more sanding.

Under the grimey carpet we found original pine floorboards and a hearth where the fireplace used to be. To get the floorboards back into shape we had to use industrial sanders which wasn’t overly fun but as with pretty much all this stuff, it was worth it in the end.

Pre-sanded floor

On top of floor sanding, we stripped the paint off the skirting, windowsill and door architrave then sanded and painted these. The radiator needed stripping and repainting too.


Finishing floorboards

Before we could varnish the floor, there were some humongous gaps between floorboards that had to be filled. To do this we glued some pine slivers in place and then chiselled & sanded them down to be flush with the floorboards.

After this it was just a case of lobbing 3 coats of varnish on and voila, floor finished.


Door dipping

One job that we couldn’t DIY was stripping the paint off the doors. It was so thick and stuck on that even with Wilkos paint/varnish stripper and a go on the heat gun we couldn’t get it off.

We got all our interior and cupboard doors picked up and dipped by a local firm. This was actually really good value and we’re so pleased with our stripped, zebra-esque doors.

Fitted wardrobe

Planning and building the wardrobe was definitely my favourite job. Don’t get me wrong, it was insanely frustrating at times but felt awesome to have made it myself and saved probably over a grand in the process.


Fireplace

We weren’t bothered about having a working fireplace in the bedroom, but the old hearth was asking for a mock cast iron fireplace to be put back in. We found one on Facebook marketplace which fit the bill. After re-tiling the hearth, we knocked back the bricked up fireplace and put her in place

Painting

The last stage before filling the room with our stuff was to give the walls, ceiling and wardrobe a lick of paint.

Finishing touches

Finally came the fun part – filling the room with stuff, including ‘smart’ hanging bedside lights and a picture ledge which you can read about and make yourself if you fancy.

Next up on the list is spare room #1 – more to follow.